There are 4 workers, possibly 5.
And I reread Dr.Bursuk's letter, they worked 6 days.
This means that they put in a total of 24 work-days to clear 1000 sq. meter,
or 41.67 sq. meter per person per day.
Please remember, this is one of the most overgrown areas of the cemetery.
Most probably the workers work together as a team; the trees and brush have
to be held by one person, cut by another one and carried away by a third
and fourth. If they worked all together, than as a group they cleared
166.67 square meter per day, or close to an area of 13m x 13m per day.
Mimi
On 5/25/09 11:46 PM, "HARDY BREIER" <HARDY3_at_BEZEQINT.NET> wrote:
> Mimi,
> How many workers are on the job?
> How many man/days until now ?
> Hardy
-----------------------------------------------------------------------------
This moderated discussion group is for information exchange on the subject of
Czernowitz and Sadagora Jewish History and Genealogy. The opinions expressed
in these posts are the opinions of the original poster only and not necessarily
the opinions of the List Owner, the Webmaster or any other members
or entities connected with this mailing list. The Czernowitz-L list has
an associated web site at http://czernowitz.ehpes.com that includes a
searchable archive of all messages posted to this list. Please post in "Plain
Text" if possible (help available at:
<http://www.jewishgen.org/InfoFiles/PlainText.html>).
To remove your address from this e-list follow the directions at
http://www.cit.cornell.edu/computer/elist/lyris/leave.html
To receive assistance for this e-list send an e-mail message to:
owner-Czernowitz-L_at_list.cornell.edu
-----------------------------------------------------------------------------
Received on 2009-05-26 04:42:54
This archive was generated by hypermail 2.2.0 : 2009-06-27 20:03:59 PDT